Slip By Page of the Slip Wizard
Use this page to specify how you want to slip the selected project or control account.
You can either slip the project or control account to a specific date or slip the selection by a number of days.
Date
Field | Description |
---|---|
Enter New Start Date | Use this field to display a calendar from which you can select a date. Cobra uses this date to calculate the number of days to slip the project or control account. Cobra calculates the difference between the earliest scheduled start date of the selected control accounts and the date entered. Cobra uses the derived duration in days to determine the new scheduled start and finish dates for each control account.
If you select a new start date, Cobra adjusts all date sets, including Schedule, Estimate, Early, and Late dates. |
Days
Field | Description |
---|---|
Days to Slip By | Use this field to slip the selected project or control account by a specific number of days. Enter a positive or negative number in this field. Cobra uses this number to determine the new scheduled start and finish dates for each control account. |
Parent Topic: Slip Wizard